Development & Planning
Project Initiatiation - Scoping
Scoping complete
Environmental Studies
Initial studies underway
Preparation of Environmental Statement
Ongoing and due to complete in early 2014
Pre-application Consultations
Initial consultations underway
Submission of Applications for Permission
Aim to submit in second half of 2014
Review of application (including Environmental Statment) by Scottish Ministers
Process takes approximately 1 year
Planning Decision: refuse or grant (with or without conditions)
Expected 2015
Implementation and monitoring
Offshore construction hoped to start in 2020, with first power output also in 2020.